| 1 | Construction of community building near Shiv Mandir in vill Religious & Cultural — GARHWA(Deputy Commissioner garhwa_IDA) - 176 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 74% of this agency's ₹23,108,788 spend went to one vendor (JE NREP MP GARHWA), across 2 vendors and 73 transactions
| GARHWA | ₹5.00 L | MEDIUM 66
delay 24duplication 20agency 15 | |
| 2 | Construction of 500 feet PCC road from main road to crematio Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - ₹750,000 against a ₹300,000 median for Roads & Paving works in GARHWA (150% above, 90 peer works)
- 681 days beyond expected completion
Read more (1 more)Show less- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹7.50 L | MEDIUM 65 | |
| 3 | Construction of 500 feet PCC road from chilbil tree to angan Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - ₹750,000 against a ₹300,000 median for Roads & Paving works in GARHWA (150% above, 90 peer works)
- 153 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹23,108,788 spend went to one vendor (JE NREP MP GARHWA), across 2 vendors and 73 transactions
| GARHWA | ₹7.50 L | MEDIUM 61 | |
| 4 | Construction of two rooms of Community Building near under c Religious & Cultural — GARHWA(Deputy Commissioner garhwa_IDA) - ₹1,000,000 against a ₹400,000 median for Religious & Cultural works in GARHWA (150% above, 9 peer works)
- 153 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹23,108,788 spend went to one vendor (JE NREP MP GARHWA), across 2 vendors and 73 transactions
| GARHWA | ₹10.00 L | MEDIUM 61 | |
| 5 | Construction of additional four rooms in High School Kharaun Education — GARHWA(Deputy Commissioner garhwa_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 673 days beyond expected completion
Read more (1 more)Show less- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹10.00 L | MEDIUM 54 | |
| 6 | Construction of 300 feet PCC road from village Arsali South Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - ₹450,000 against a ₹300,000 median for Roads & Paving works in GARHWA (50% above, 90 peer works)
- 679 days beyond expected completion
Read more (1 more)Show less- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹4.50 L | MEDIUM 53 | |
| 7 | Construction of 300 feet PCC road from Munarik house to Shiv Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - ₹450,000 against a ₹300,000 median for Roads & Paving works in GARHWA (50% above, 90 peer works)
- 184 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹23,108,788 spend went to one vendor (JE NREP MP GARHWA), across 2 vendors and 73 transactions
| GARHWA | ₹4.50 L | MEDIUM 53 | |
| 8 | Construction of 300 feet PCC road from Var tree to pond in Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - ₹450,000 against a ₹300,000 median for Roads & Paving works in GARHWA (50% above, 90 peer works)
- 176 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹23,108,788 spend went to one vendor (JE NREP MP GARHWA), across 2 vendors and 73 transactions
| GARHWA | ₹4.50 L | MEDIUM 52 | |
| 9 | Construction of 300 feet PCC road from Ramchandr Sah house t Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - ₹450,000 against a ₹300,000 median for Roads & Paving works in GARHWA (50% above, 90 peer works)
- 170 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹23,108,788 spend went to one vendor (JE NREP MP GARHWA), across 2 vendors and 73 transactions
| GARHWA | ₹4.50 L | MEDIUM 51 | |
| 10 | Hand pump installation near Ramakant Paswan's house in villa Water — GARHWA(Deputy Commissioner garhwa_IDA) - 680 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹1.50 L | MEDIUM 49 | |
| 11 | Installation of a deep bore and a hand pump in Saraswati Shi Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - 681 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹3.50 L | MEDIUM 49 | |
| 12 | Construction of bath house in village Hoor Bagicha Drainage & Sanitation — GARHWA(Deputy Commissioner garhwa_IDA) - 673 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹1.50 L | MEDIUM 49 | |
| 13 | Construction of deep bore near the farm of Sudhir Chaubey in Water — GARHWA(Deputy Commissioner garhwa_IDA) - 680 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹2.00 L | MEDIUM 49 | |
| 14 | Construction of deep bore near the farm of village Kharondhi Water — GARHWA(Deputy Commissioner garhwa_IDA) - 680 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹2.00 L | MEDIUM 49 | |
| 15 | Construction of deep bore near Bajrang Prasad's farm in vill Water — GARHWA(Deputy Commissioner garhwa_IDA) - 680 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹2.00 L | MEDIUM 49 | |
| 16 | Construction of deep bore near Banshi Ram's farm in village Water — GARHWA(Deputy Commissioner garhwa_IDA) - 681 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹2.00 L | MEDIUM 49 | |
| 17 | Construction of deep bore near Munna Chaudhary's farm in vil Water — GARHWA(Deputy Commissioner garhwa_IDA) - 681 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹2.00 L | MEDIUM 49 | |
| 18 | Construction of 300 feet PCC road from Hanuman Mandir to Dev Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - ₹450,000 against a ₹300,000 median for Roads & Paving works in GARHWA (50% above, 90 peer works)
- 153 days beyond expected completion
Read more (1 more)Show less- 74% of this agency's ₹23,108,788 spend went to one vendor (JE NREP MP GARHWA), across 2 vendors and 73 transactions
| GARHWA | ₹4.50 L | MEDIUM 49 | |
| 19 | Construction of 200 feet PCC road from Lepa Bhuiyan's house Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - 680 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹3.00 L | MEDIUM 49 | |
| 20 | Construction of 200 feet PCC road from Ambika Ram's house to Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - 680 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹3.00 L | MEDIUM 49 | |
| 21 | Construction of 200 feet PCC road from Devi Mandir to PCC ro Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - 680 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹3.00 L | MEDIUM 49 | |
| 22 | Construction of 200 feet PCC road in Bablu Singha's locality Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - 680 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹3.00 L | MEDIUM 49 | |
| 23 | Construction of 200 feet PCC road from village Kalyanpur Ram Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - 681 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹3.00 L | MEDIUM 49 | |
| 24 | Construction of 200 feet PCC road from Barwahi School to can Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - 681 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹3.00 L | MEDIUM 49 | |
| 25 | Construction of 200 feet PCC road from bamboo to Var river i Roads & Paving — GARHWA(Deputy Commissioner garhwa_IDA) - 681 days beyond expected completion
- 92% of this agency's ₹23,649,763 spend went to one vendor (SUDIP RAM), across 2 vendors and 76 transactions
| GARHWA | ₹3.00 L | MEDIUM 49 | |