| 1 | Development of public park. Sports — GADAG(Deputy Commsioner Gadag_ida) - 289 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 68
delay 25duplication 20agency 15 | |
| 2 | KALMESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 190 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 67
delay 25duplication 20agency 15 | |
| 3 | KALMESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 67
delay 25duplication 20agency 15 | |
| 4 | KALMESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 147 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 61
delay 20duplication 20agency 15 | |
| 5 | Development of public park. Sports — GADAG(Deputy Commsioner Gadag_ida) - 289 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| GADAG | ₹5.00 L | MEDIUM 59
delay 25duplication 20cost 8 | |
| 6 | Construction of Community Hall. Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 120 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹6.00 L | MEDIUM 58
duplication 20delay 17agency 15 | |
| 7 | Construction of Community Hall. Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 120 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹4.50 L | MEDIUM 57
duplication 20delay 17agency 15 | |
| 8 | Construction of BUS SHELTER in HOLE ALUR New shifted Village Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹800,000 against a ₹500,000 median for Community Buildings works in GADAG (60% above, 86 peer works)
- 183 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹8.00 L | MEDIUM 55 | |
| 9 | Construction of Community Hall in SURAKOD Village, Property Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
- 87 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 52 | |
| 10 | CONSTRUCTION OF CONCRETE ROAD Roads & Paving — GADAG(Deputy Commsioner Gadag_ida) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 191 days beyond expected completion
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹15.00 L | MEDIUM 52 | |
| 11 | Construction of Community Hall. Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 120 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| GADAG | ₹6.00 L | MEDIUM 50
duplication 20delay 17cost 7 | |
| 12 | Construction of Community Hall. Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 120 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 42% delay rate across its projects
| GADAG | ₹4.50 L | MEDIUM 48
duplication 20delay 17agency 6 | |
| 13 | MANJUNATH SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 208 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 14 | HINGULAMBIKA SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 208 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 15 | MADIWAL MACHAYYA SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 208 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 16 | MARUTI SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 190 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 17 | VEERABHADRESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 190 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 18 | NANDI BASAVESHWAR SEVA SAMITI SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 19 | BEERALINGESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 20 | BISEROTTI VEERABHADRESHWAR SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 21 | GRAMADEVI DYAMAVVA DEVI SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 22 | SEVALAL SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 191 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 23 | Construction of Community Hall in MALAWAD Village, Property Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 183 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 24 | Construction of Community Hall in HUNASHIKATTI Village Prope Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - 182 days beyond expected completion
- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹5.00 L | MEDIUM 47 | |
| 25 | GRAM DEVI SABHA BHAVAN Community Buildings — GADAG(Deputy Commsioner Gadag_ida) - Completed work has no photographic documentation on record
- ₹1,000,000 against a ₹500,000 median for Community Buildings works in GADAG (100% above, 86 peer works)
Read more (1 more)Show less- 100% of this agency's ₹24,400,000 spend went to one vendor (Project Manager Nirmiti kendra gadag), across 1 vendor and 62 transactions
| GADAG | ₹10.00 L | MEDIUM 45
cost 25agency 15compliance 5 | |