| 1 | Installation of Solar High Mast LIght at Pookattupadi Juncti Street Lighting — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹449,000 against a ₹200,000 median for Street Lighting works in ERNAKULAM (124% above, 343 peer works)
- 249 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹4.49 L | HIGH 75
cost 25delay 25duplication 20 | |
| 2 | Construction Mutholapuram Pulingunnumala- Vettiyodi Drinking Water — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹2,500,000 against a ₹1,000,000 median for Water works in ERNAKULAM (150% above, 9 peer works)
- 274 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹25.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 3 | Construction of Artificial Football turf, Municipal Stadium Sports — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹15,380,000 against a ₹2,291,551 median for Sports works in ERNAKULAM (571% above, 23 peer works)
- 350 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹1.54 Cr | HIGH 75
cost 25delay 25duplication 20 | |
| 4 | Installation of Solar High Mast LIght at Pookattupadi Juncti Street Lighting — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹449,000 against a ₹200,000 median for Street Lighting works in ERNAKULAM (124% above, 343 peer works)
- 249 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹4.49 L | HIGH 75
cost 25delay 25duplication 20 | |
| 5 | Construction Mutholapuram Pulingunnumala- Vettiyodi Drinking Water — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹2,500,000 against a ₹1,000,000 median for Water works in ERNAKULAM (150% above, 9 peer works)
- 274 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹25.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 6 | Construction of Artificial Football turf, Municipal Stadium Sports — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹15,380,000 against a ₹2,291,551 median for Sports works in ERNAKULAM (571% above, 23 peer works)
- 350 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹1.54 Cr | HIGH 75
cost 25delay 25duplication 20 | |
| 7 | Construction of Mattakadu XIME College road or pathway, ward Roads & Paving — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in ERNAKULAM (200% above, 192 peer works)
- 179 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹15.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 8 | Construction of Mattakadu XIME College road or pathway, ward Roads & Paving — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in ERNAKULAM (200% above, 192 peer works)
- 179 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹15.00 L | HIGH 75
cost 25delay 25duplication 20 | |
| 9 | Installation of High Mast Light in Mattakkad Xime college J Street Lighting — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹550,000 against a ₹200,000 median for Street Lighting works in ERNAKULAM (175% above, 343 peer works)
- 131 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹5.50 L | MEDIUM 68
cost 25duplication 20delay 18 | |
| 10 | Installation of High Mast Light in Parappuram Jn , Mullanku Street Lighting — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹550,000 against a ₹200,000 median for Street Lighting works in ERNAKULAM (175% above, 343 peer works)
- 131 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹5.50 L | MEDIUM 68
cost 25duplication 20delay 18 | |
| 11 | Installation of High Mast Light in Mattakkad Xime college J Street Lighting — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹550,000 against a ₹200,000 median for Street Lighting works in ERNAKULAM (175% above, 343 peer works)
- 131 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹5.50 L | MEDIUM 68
cost 25duplication 20delay 18 | |
| 12 | Installation of High Mast Light in Parappuram Jn , Mullanku Street Lighting — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹550,000 against a ₹200,000 median for Street Lighting works in ERNAKULAM (175% above, 343 peer works)
- 131 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹5.50 L | MEDIUM 68
cost 25duplication 20delay 18 | |
| 13 | Installation of High Mast Light at Navodayapuram Jn Cat SC Street Lighting — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹395,500 against a ₹200,000 median for Street Lighting works in ERNAKULAM (98% above, 343 peer works)
- 113 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹3.96 L | MEDIUM 65
cost 24duplication 20delay 16 | |
| 14 | Installation of High Mast Light at Navodayapuram Jn Cat SC Street Lighting — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹395,500 against a ₹200,000 median for Street Lighting works in ERNAKULAM (98% above, 343 peer works)
- 113 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹3.96 L | MEDIUM 65
cost 24duplication 20delay 16 | |
| 15 | Installation of High Mast Light at Pezhakkapilly - Pallipadi Street Lighting — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹548,000 against a ₹200,000 median for Street Lighting works in ERNAKULAM (174% above, 343 peer works)
- 102 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹5.48 L | MEDIUM 64
cost 25duplication 20delay 14 | |
| 16 | Installation of High Mast Light at Pezhakkapilly - Pallipadi Street Lighting — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹548,000 against a ₹200,000 median for Street Lighting works in ERNAKULAM (174% above, 343 peer works)
- 102 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹5.48 L | MEDIUM 64
cost 25duplication 20delay 14 | |
| 17 | Construction of Science Laboratory at little flower high sch Education — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 179 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹17.00 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 18 | Construction of Science Laboratory at little flower high sch Education — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 179 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹17.00 L | MEDIUM 63
delay 25duplication 20cost 13 | |
| 19 | Construction of first floor of the building of Kannan Nair S Roads & Paving — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in ERNAKULAM (100% above, 192 peer works)
- 85 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹10.00 L | MEDIUM 62
cost 25duplication 20delay 12 | |
| 20 | Construction of first floor of the building of Kannan Nair S Roads & Paving — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - ₹1,000,000 against a ₹500,000 median for Roads & Paving works in ERNAKULAM (100% above, 192 peer works)
- 85 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹10.00 L | MEDIUM 62
cost 25duplication 20delay 12 | |
| 21 | Construction of new building for Anganavadi, ward no.04, Kad Community Buildings — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 179 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹15.00 L | MEDIUM 62
delay 25duplication 20cost 12 | |
| 22 | Construction of new building for Anganavadi, ward no.04, Kad Community Buildings — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 179 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| ERNAKULAM | ₹15.00 L | MEDIUM 62
delay 25duplication 20cost 12 | |
| 23 | Construction of Open Gym and Installation of Equipments at C Sports — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - 229 days beyond expected completion
- 100% similarity with another nearby work
| ERNAKULAM | ₹5.00 L | MEDIUM 57
delay 25duplication 20cost 7 | |
| 24 | Construction of Open Gym and Installation of Equipments at C Sports — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - 229 days beyond expected completion
- 100% similarity with another nearby work
| ERNAKULAM | ₹5.00 L | MEDIUM 57
delay 25duplication 20cost 7 | |
| 25 | She space and Gym at ward-10 of Thuravur GramaPanchayat,Erna Sports — ERNAKULAM(DISTRICT COLLECTOR ERNAKULAM_IDA) - 229 days beyond expected completion
- 100% similarity with another nearby work
| ERNAKULAM | ₹2.21 L | MEDIUM 57
delay 25duplication 20cost 7 | |