| 1 | Supply & Installation of Swing & Slide Sports — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 833 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| DHALAI | ₹75.00 L | HIGH 74
delay 25cost 23duplication 20 | |
| 2 | Supply & Installation of Stainless Steel Water Tank- G304 wi Water — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 833 days beyond expected completion
| DHALAI | ₹1.05 Cr | MEDIUM 55 | |
| 3 | Formation of link road made of interlocking pavers block inc Roads & Paving — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 759 days beyond expected completion
| DHALAI | ₹29.33 L | MEDIUM 50 | |
| 4 | Construction of Prefabricated shop and solar street lights a Street Lighting — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 214 days beyond expected completion
| DHALAI | ₹54.79 L | MEDIUM 50 | |
| 5 | Construction of Additional Class Room at 82-Miles Jawahar Na Education — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 832 days beyond expected completion
| DHALAI | ₹21.80 L | MEDIUM 50 | |
| 6 | construction of sports complex in convergence with mgnrega a Sports — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 280 days beyond expected completion
| DHALAI | ₹40.00 L | MEDIUM 49 | |
| 7 | Supply & Installation of Stainless Steel Mess Table Equipment & Vehicles — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - ₹8,490,000 against a ₹5,903,150 median for Equipment & Vehicles works in DHALAI (44% above, 10 peer works)
- 100% similarity with another nearby work
| DHALAI | ₹84.90 L | MEDIUM 48
cost 22duplication 20agency 6 | |
| 8 | Supply & Installation of Stainless Steel Mess Table Equipment & Vehicles — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - ₹8,490,000 against a ₹5,903,150 median for Equipment & Vehicles works in DHALAI (44% above, 10 peer works)
- 100% similarity with another nearby work
| DHALAI | ₹84.90 L | MEDIUM 48
cost 22duplication 20agency 6 | |
| 9 | Supply & Installation of Swing & Slide Sports — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 100% similarity with another nearby work
| DHALAI | ₹74.13 L | MEDIUM 47
cost 22duplication 20agency 6 | |
| 10 | Supply of Garbage battery E- Rickshaw Equipment & Vehicles — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 100% similarity with another nearby work
| DHALAI | ₹58.99 L | MEDIUM 47
cost 21duplication 20agency 6 | |
| 11 | construction of experiential learning centre at Sundarban Am Education — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 280 days beyond expected completion
| DHALAI | ₹20.00 L | MEDIUM 45 | |
| 12 | Supply Installation & Commissioning of 25 nos Solar Street L Street Lighting — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 760 days beyond expected completion
| DHALAI | ₹5.40 L | MEDIUM 43 | |
| 13 | Supply Installation & Commissioning of 20 Nos Solar Street L Street Lighting — Dhalai(DISTRICT MAGISTRATE DHALAI_IDA) - 697 days beyond expected completion
| DHALAI | ₹4.32 L | MEDIUM 40 | |