| 1 | C/o additional rooms in GHS Phindru, VPO Phindru, Dev. Block Education — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹250,000 median for Education works in CHAMBA (100% above, 23 peer works)
- 324 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 2 | Construction of Concrete Road Adarsh Nagar Hardaspura Ward p Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (150% above, 339 peer works)
- 373 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 3 | Construction of ambulance road soling conc. With drain main Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (100% above, 339 peer works)
- 412 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 4 | Pucca path from Chalang to Shamshan Ghat GP Chil Bangla Dev. Religious & Cultural — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Religious & Cultural works in CHAMBA (100% above, 38 peer works)
- 413 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 5 | Jeep Road from Khalotu to Bairi GP Chil Bangla Dev. Block Ch Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (100% above, 339 peer works)
- 413 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 6 | C/o additional rooms in GHS Phindru, VPO Phindru, Dev. Block Education — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹250,000 median for Education works in CHAMBA (100% above, 23 peer works)
- 324 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 7 | Construction of Concrete Road Adarsh Nagar Hardaspura Ward p Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (150% above, 339 peer works)
- 373 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 8 | Construction of ambulance road soling conc. With drain main Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (100% above, 339 peer works)
- 412 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 9 | Pucca path from Chalang to Shamshan Ghat GP Chil Bangla Dev. Religious & Cultural — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Religious & Cultural works in CHAMBA (100% above, 38 peer works)
- 413 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 10 | Jeep Road from Khalotu to Bairi GP Chil Bangla Dev. Block Ch Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (100% above, 339 peer works)
- 413 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | HIGH 76
cost 25delay 25duplication 20 | |
| 11 | Construction of Play Ground Safety Wall Boundary & Protection — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹300,000 against a ₹150,000 median for Boundary & Protection works in CHAMBA (100% above, 60 peer works)
- 131 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹3.00 L | MEDIUM 69
cost 25duplication 20delay 18 | |
| 12 | Construction of Play Ground Safety Wall Boundary & Protection — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹300,000 against a ₹150,000 median for Boundary & Protection works in CHAMBA (100% above, 60 peer works)
- 131 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹3.00 L | MEDIUM 69
cost 25duplication 20delay 18 | |
| 13 | Construction of Check Dam Uppper Baniyad, in Gram Panchayat Water — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹250,000 median for Water works in CHAMBA (100% above, 13 peer works)
- 129 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | MEDIUM 69
cost 25duplication 20delay 18 | |
| 14 | Construction of Pulli Bridge Pro. Work at Sarotha Nallah Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (150% above, 339 peer works)
- 129 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | MEDIUM 69
cost 25duplication 20delay 18 | |
| 15 | Construction of Check Dam Uppper Baniyad, in Gram Panchayat Water — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹250,000 median for Water works in CHAMBA (100% above, 13 peer works)
- 129 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | MEDIUM 69
cost 25duplication 20delay 18 | |
| 16 | Construction of Pulli Bridge Pro. Work at Sarotha Nallah Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹500,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (150% above, 339 peer works)
- 129 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹5.00 L | MEDIUM 69
cost 25duplication 20delay 18 | |
| 17 | Construction of Community Centre at Village and Gram Panchay Community Buildings — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹900,000 against a ₹300,000 median for Community Buildings works in CHAMBA (200% above, 100 peer works)
- 121 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹9.00 L | MEDIUM 68
cost 25duplication 20delay 17 | |
| 18 | Construction of Community Centre at Village and Gram Panchay Community Buildings — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹900,000 against a ₹300,000 median for Community Buildings works in CHAMBA (200% above, 100 peer works)
- 121 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹9.00 L | MEDIUM 68
cost 25duplication 20delay 17 | |
| 19 | construction work of Additional Rooms Education — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹250,000 median for Education works in CHAMBA (60% above, 23 peer works)
- 333 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | MEDIUM 66
delay 25duplication 20cost 15 | |
| 20 | construction work of Additional Rooms Education — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹400,000 against a ₹250,000 median for Education works in CHAMBA (60% above, 23 peer works)
- 333 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹4.00 L | MEDIUM 66
delay 25duplication 20cost 15 | |
| 21 | Development of playfields and sports ground Sports — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹300,000 against a ₹200,000 median for Sports works in CHAMBA (50% above, 32 peer works)
- 218 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹3.00 L | MEDIUM 64
delay 25duplication 20cost 13 | |
| 22 | construction work of Cremation ground for public convenience Religious & Cultural — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹300,000 against a ₹200,000 median for Religious & Cultural works in CHAMBA (50% above, 38 peer works)
- 333 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹3.00 L | MEDIUM 64
delay 25duplication 20cost 13 | |
| 23 | Construction of Pucca path Vill. Hadotha GP Bhanauta Dev. Bl Roads & Paving — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹300,000 against a ₹200,000 median for Roads & Paving works in CHAMBA (50% above, 339 peer works)
- 412 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹3.00 L | MEDIUM 64
delay 25duplication 20cost 13 | |
| 24 | Development of playfields and sports ground Sports — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹300,000 against a ₹200,000 median for Sports works in CHAMBA (50% above, 32 peer works)
- 218 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹3.00 L | MEDIUM 64
delay 25duplication 20cost 13 | |
| 25 | construction work of Cremation ground for public convenience Religious & Cultural — CHAMBA(DEPUTY COMMISSIONER CHAMBA_IDA) - ₹300,000 against a ₹200,000 median for Religious & Cultural works in CHAMBA (50% above, 38 peer works)
- 333 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 40% delay rate across its projects
| CHAMBA | ₹3.00 L | MEDIUM 64
delay 25duplication 20cost 13 | |