| 1 | Construction of Community Hall Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,500,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (200% above, 447 peer works)
- 609 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹15.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 2 | Construction of Sanskrutika Bhavan near Shri Basaveshwar Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (100% above, 447 peer works)
- 561 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 3 | Construction of Sanskrutika Bhavan near Shri Veerbhadreshwar Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (100% above, 447 peer works)
- 619 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹10.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 4 | Construction of Community Hall Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,500,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (200% above, 447 peer works)
- 609 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹15.00 L | HIGH 77
cost 25delay 25duplication 20 | |
| 5 | Construction of Sanskrutika Bhavan near Shri Veerbhdreshwa Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (100% above, 447 peer works)
- 561 days beyond expected completion
Read more (2 more)Show less- 99% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹10.00 L | HIGH 74
cost 25delay 25duplication 16 | |
| 6 | Road construction work Roads & Paving — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in BELAGAVI (200% above, 59 peer works)
- 146 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹15.00 L | HIGH 73
cost 25delay 20duplication 20 | |
| 7 | Road construction work Roads & Paving — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in BELAGAVI (200% above, 59 peer works)
- 146 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹15.00 L | HIGH 73
cost 25delay 20duplication 20 | |
| 8 | Construction of Sanskrutika Bhavan near Shri Mahanta Duradun Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in BELAGAVI (100% above, 447 peer works)
- 561 days beyond expected completion
Read more (2 more)Show less- 97% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹10.00 L | MEDIUM 67
cost 25delay 25duplication 9 | |
| 9 | Construction of Cultural Hall Near Shri Hanuman Temple Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 691 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹5.00 L | MEDIUM 62
delay 25duplication 20cost 10 | |
| 10 | Construction of Cultural Hall Near Shri Laxmi Temple Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 698 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹5.00 L | MEDIUM 62
delay 25duplication 20cost 10 | |
| 11 | Construction of Cultural Hall Near
Shri Mahadev Temple Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 698 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹5.00 L | MEDIUM 62
delay 25duplication 20cost 10 | |
| 12 | Construction of HiTech Bus Shelter Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 698 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹4.50 L | MEDIUM 62
delay 25duplication 20cost 10 | |
| 13 | Construction of HiTech Bus Shelter Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 698 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹4.50 L | MEDIUM 62
delay 25duplication 20cost 10 | |
| 14 | Construction of HiTech Bus Shelter Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 698 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹4.50 L | MEDIUM 62
delay 25duplication 20cost 10 | |
| 15 | Construction of Cultural Hall Near Shri Basaveshwar Temple Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 697 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹4.00 L | MEDIUM 62
delay 25duplication 20cost 9 | |
| 16 | Construction of Cultural Hall Near Shri Hanuman Temple Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 697 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹4.00 L | MEDIUM 62
delay 25duplication 20cost 9 | |
| 17 | Construction of Cultural Hall Near Shri Basaveshwar Temple Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 697 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹3.00 L | MEDIUM 61
delay 25duplication 20cost 9 | |
| 18 | Construction of Cultural Hall Near Shri Mahalaxmi Temple Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 697 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹3.00 L | MEDIUM 61
delay 25duplication 20cost 9 | |
| 19 | Construction of Cultural Hall Near Shri Basaveshwar Temple Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 697 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹3.00 L | MEDIUM 61
delay 25duplication 20cost 9 | |
| 20 | Construction of Cultural Hall Near Shri Mahalaxmi Temple Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 697 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹3.00 L | MEDIUM 61
delay 25duplication 20cost 9 | |
| 21 | Construction of Cultural Hall Near Shri Hanuman Temple Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 643 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹5.00 L | MEDIUM 61
delay 25duplication 20cost 9 | |
| 22 | Construction of Cultural Hall Near Shri Vithal Rukmini Templ Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 697 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹2.50 L | MEDIUM 61
delay 25duplication 20cost 9 | |
| 23 | Construction of Sanskrutika Bhavan near Shri Bandemma Devi T Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 630 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹5.00 L | MEDIUM 61
delay 25duplication 20cost 9 | |
| 24 | Construction of Sanskrutika Bhavan near Shri Veerbhadreshwar Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 629 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹5.00 L | MEDIUM 61
delay 25duplication 20cost 8 | |
| 25 | Construction of Sanskrutika Bhavan near Shri Walmiki Temple Community Buildings — BELAGAVI(DEPUTY COMMISSIONER BELGAUM_IDA) - 548 days beyond expected completion
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 49% delay rate across its projects
| BELAGAVI | ₹5.00 L | MEDIUM 61
delay 25duplication 20cost 8 | |