| 1 | Construction of Road from Natunbasti to Ahom pathar via to d Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹2,000,000 against a ₹500,000 median for Roads & Paving works in BARPETA (300% above, 143 peer works)
- 365 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹20.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 2 | Construction of road from PWD road to Prodip Das house near Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,200,000 against a ₹500,000 median for Roads & Paving works in BARPETA (140% above, 143 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹12.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 3 | Construction of Road from Natunbasti to Ahom pathar via to d Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹2,000,000 against a ₹500,000 median for Roads & Paving works in BARPETA (300% above, 143 peer works)
- 365 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹20.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 4 | Construction of road from PWD road to Prodip Das house near Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,200,000 against a ₹500,000 median for Roads & Paving works in BARPETA (140% above, 143 peer works)
- 450 days beyond expected completion
Read more (2 more)Show less- 100% similarity with another nearby work
- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹12.00 L | HIGH 78
cost 25delay 25duplication 20 | |
| 5 | Construction of Girls Common Room of Kalgachia College of Co Education — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,000,000 against a ₹500,000 median for Education works in BARPETA (100% above, 38 peer works)
- 741 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹10.00 L | MEDIUM 58 | |
| 6 | Construction of Char Chapari Museum Religious & Cultural — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in BARPETA (100% above, 14 peer works)
- 794 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹10.00 L | MEDIUM 58 | |
| 7 | Upgradation of community hall near Maa Manasha mandir at Pat Community Buildings — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,000,000 against a ₹500,000 median for Community Buildings works in BARPETA (100% above, 15 peer works)
- 236 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹10.00 L | MEDIUM 58 | |
| 8 | Construction of Community Hall near AGP Office, Barpeta (Pha Community Buildings — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,500,000 against a ₹500,000 median for Community Buildings works in BARPETA (200% above, 15 peer works)
- 236 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹15.00 L | MEDIUM 58 | |
| 9 | Construction of T.R.Phookan Smriti Rangamancha at Barpeta Religious & Cultural — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹14,000,000 against a ₹500,000 median for Religious & Cultural works in BARPETA (2700% above, 14 peer works)
- 236 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹1.40 Cr | MEDIUM 58 | |
| 10 | Construction of cultural project at Panchagram Rash Khola at Religious & Cultural — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,000,000 against a ₹500,000 median for Religious & Cultural works in BARPETA (100% above, 14 peer works)
- 236 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹10.00 L | MEDIUM 58 | |
| 11 | Construction of Road from B.B linked road to Upen Das house Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹2,500,000 against a ₹500,000 median for Roads & Paving works in BARPETA (400% above, 143 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹25.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 12 | Construction of road from Basu Das House to Dipak Das House Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,100,000 against a ₹500,000 median for Roads & Paving works in BARPETA (120% above, 143 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹11.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 13 | Construction of Road from Pradip Das house to Uday Basumatar Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in BARPETA (200% above, 143 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹15.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 14 | Const. of road from B.S. Link Road to Ram Das house at Sundo Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in BARPETA (200% above, 143 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹15.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 15 | Construction of Road from B.P.linked Road to Shiva Mandir at Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in BARPETA (200% above, 143 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹15.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 16 | Const of road from Ajibul Ali house to Haidar Ali Ahmed at K Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹900,000 against a ₹500,000 median for Roads & Paving works in BARPETA (80% above, 143 peer works)
- 594 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹9.00 L | MEDIUM 53 | |
| 17 | Const of road from Abdul Sama house to Saimuddin Ali house a Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹900,000 against a ₹500,000 median for Roads & Paving works in BARPETA (80% above, 143 peer works)
- 601 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹9.00 L | MEDIUM 53 | |
| 18 | Construction of Road from B.B linked road to Upen Das house Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹2,500,000 against a ₹500,000 median for Roads & Paving works in BARPETA (400% above, 143 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹25.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 19 | Construction of road from Basu Das House to Dipak Das House Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,100,000 against a ₹500,000 median for Roads & Paving works in BARPETA (120% above, 143 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹11.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 20 | Construction of Road from Pradip Das house to Uday Basumatar Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in BARPETA (200% above, 143 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹15.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 21 | Const. of road from B.S. Link Road to Ram Das house at Sundo Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in BARPETA (200% above, 143 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹15.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 22 | Construction of Road from B.P.linked Road to Shiva Mandir at Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹1,500,000 against a ₹500,000 median for Roads & Paving works in BARPETA (200% above, 143 peer works)
- 100% similarity with another nearby work
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹15.00 L | MEDIUM 53
cost 25duplication 20agency 8 | |
| 23 | Ambulance for Barpeta Kirtan Ghar to be Managed by Barpeta S Health — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 751 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹9.35 L | MEDIUM 48 | |
| 24 | Constructon of Rangamancha at Jania Satra complex Religious & Cultural — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 800 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹7.00 L | MEDIUM 48 | |
| 25 | Const of road from Manoj Das house Somarkhat to Amit Ali hou Roads & Paving — BARPETA(DEPUTY COMMISSIONER BARPETA 1) - ₹800,000 against a ₹500,000 median for Roads & Paving works in BARPETA (60% above, 143 peer works)
- 601 days beyond expected completion
Read more (1 more)Show less- Implementing agency has a 50% delay rate across its projects
| BARPETA | ₹8.00 L | MEDIUM 48 | |