| 1 | Construction of Community Hall in Ambedkar Nagar area for Sc Community Buildings — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹987,644 against a ₹500,000 median for Community Buildings works in AMRELI (98% above, 55 peer works)
- 171 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹9.88 L | HIGH 70
cost 24delay 24duplication 20 | |
| 2 | For the construction of a cultural hall (community hall) for Community Buildings — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹987,644 against a ₹500,000 median for Community Buildings works in AMRELI (98% above, 55 peer works)
- 171 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹9.88 L | HIGH 70
cost 24delay 24duplication 20 | |
| 3 | Construction of Community Hall in Ambedkar Nagar area for Sc Community Buildings — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹987,644 against a ₹500,000 median for Community Buildings works in AMRELI (98% above, 55 peer works)
- 171 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹9.88 L | HIGH 70
cost 24delay 24duplication 20 | |
| 4 | For the construction of a cultural hall (community hall) for Community Buildings — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹987,644 against a ₹500,000 median for Community Buildings works in AMRELI (98% above, 55 peer works)
- 171 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹9.88 L | HIGH 70
cost 24delay 24duplication 20 | |
| 5 | For work of Block Road from Yogichok Bridge River Bank to Ol Roads & Paving — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹499,700 against a ₹300,000 median for Roads & Paving works in AMRELI (67% above, 359 peer works)
- 238 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹5.00 L | MEDIUM 64
delay 25duplication 20cost 17 | |
| 6 | For work of Block Road from Yogichok Bridge River Bank to Ol Roads & Paving — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹499,700 against a ₹300,000 median for Roads & Paving works in AMRELI (67% above, 359 peer works)
- 238 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹5.00 L | MEDIUM 64
delay 25duplication 20cost 17 | |
| 7 | Fitting of Sitting RCC Benches at Amrit Sarovar Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 57
delay 25duplication 20cost 10 | |
| 8 | Fitting of Sitting RCC Benches at Amrit Sarovar Nos.4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 57
delay 25duplication 20cost 10 | |
| 9 | Fitting of Sitting RCC Benches at Amrit Sarovar Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 57
delay 25duplication 20cost 10 | |
| 10 | Fitting of Sitting RCC Benches at Amrit Sarovar Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 57
delay 25duplication 20cost 10 | |
| 11 | Fitting of Sitting RCC Benches at Amrit Sarovar Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 57
delay 25duplication 20cost 10 | |
| 12 | Fitting of Sitting RCC Benches at Amrit Sarovar Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 57
delay 25duplication 20cost 10 | |
| 13 | Fitting of Sitting RCC Benches at Amrit Sarovar Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 57
delay 25duplication 20cost 10 | |
| 14 | Fitting of Sitting RCC Benches at Amrit Sarovar Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 57
delay 25duplication 20cost 10 | |
| 15 | Fitting of Sitting RCC Benches at Amrit Sarovar Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 57
delay 25duplication 20cost 10 | |
| 16 | Fitting of Sitting RCC Benches at Amrit Sarovar Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 57
delay 25duplication 20cost 10 | |
| 17 | Fitting of Sitting RCC Benches at Amrit Sarovar Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 57
delay 25duplication 20cost 10 | |
| 18 | Grant of Paver block work on the dirt road to reach the Shi Roads & Paving — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹499,700 against a ₹300,000 median for Roads & Paving works in AMRELI (67% above, 359 peer works)
- 126 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹5.00 L | MEDIUM 56
duplication 20delay 18cost 17 | |
| 19 | Grant of Paver block work on the dirt road to reach the Shi Roads & Paving — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - ₹499,700 against a ₹300,000 median for Roads & Paving works in AMRELI (67% above, 359 peer works)
- 126 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹5.00 L | MEDIUM 56
duplication 20delay 18cost 17 | |
| 20 | shambhupara gam crematorium Shead Work Religious & Cultural — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - 273 days beyond expected completion
- 100% similarity with another nearby work
| AMRELI | ₹1.00 L | MEDIUM 56
delay 25duplication 20cost 9 | |
| 21 | shambhupara gam crematorium Shead Work Religious & Cultural — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - 273 days beyond expected completion
- 100% similarity with another nearby work
| AMRELI | ₹1.00 L | MEDIUM 56
delay 25duplication 20cost 9 | |
| 22 | Fitting of Sitting RCC Benches at Amrit Sarovar-1 Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 56
delay 25duplication 19cost 10 | |
| 23 | Fitting of Sitting RCC Benches at Amrit Sarovar-2 Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 56
delay 25duplication 19cost 10 | |
| 24 | Fitting of Sitting RCC Benches at Amrut Sarovar Nos.4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 56
delay 25duplication 18cost 10 | |
| 25 | Fitting of Sitting RCC Benches at Amrut Sarovar 1 Nos. 4 Equipment & Vehicles — AMRELI(DISTRICT COLLECTOR AMRELI_IDA) - Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of range
- 632 days beyond expected completion
Read more (1 more)Show less- 100% similarity with another nearby work
| AMRELI | ₹14,200 | MEDIUM 56
delay 25duplication 18cost 10 | |