Road Upgrading Work in Dabpal Main Road to Jhakadi Ladi, Gra

Roads & Paving

Chhattisgarh / BASTAR — BASTAR(DISTRICT COLLECTOR BASTAR_IDA) · Deepak Baij (BASTAR)

Road Upgrading Work in Dabpal Main Road to Jhakadi Ladi, Gram Panchyat Badanji-2.

Overall risk score
53/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication0
Agency23
Compliance0
Sanctioned
₹19.98 L
Delay
582d
Cost deviation
185%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹1,998,000 against a ₹700,000 median for Roads & Paving works in BASTAR (185% above, 70 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 582 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.