Construction of Community Hall Building at Dharmapura Villag

Community Buildings

Karnataka / CHITRADURGA — CHITRADURGA(DEPUTY COMMISSIONER CHITRADURGA_IDA) · Narayana Swamy Abbaiah (CHITRADURGA)

Construction of Community Hall Building at Dharmapura Village (S.C.)

Overall risk score
59/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication0
Agency59
Compliance0
Sanctioned
₹10.00 L
Delay
579d
Cost deviation
100%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹1,000,000 against a ₹500,000 median for Community Buildings works in CHITRADURGA (100% above, 153 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 579 days beyond expected completionPublished dates
  • Implementing agency has a 59% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.