work of bore with motor in Nishal Faliya
Water
Gujarat / DAHOD — Dahod(DISTRICT COLLECTOR DOHAD_IDA) · Jaswantsinh Sumanbhai Bhabhor (DAHOD)
Overall risk score
58/100
Blended from the five components below, each weighted as shown.
Risk components
Cost37
Delay100
Duplication78
Agency54
Compliance0
Sanctioned
₹55,000
Delay
589d
Cost deviation
-78%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- 589 days beyond expected completionPublished dates
- 99% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)
- Implementing agency has a 54% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.
Reads as a near-duplicate of work #23338 (sentence-embedding similarity 0.99, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)