2nd Inst. 2022-23:-Construction of Footpath for Umjajew, Ma

Roads & Paving

Meghalaya / EAST KHASI HILLS — EAST KHASI HILLS(Deputy Commissioner, East Khasi Hills District) · Vincent H. Pala (SHILLONG)

2nd Inst. 2022-23:-Construction of Footpath for Umjajew, Mawlai.

Overall risk score
38/100
Blended from the five components below, each weighted as shown.
LOW

Risk components

Cost37
Delay100
Duplication0
Agency24
Compliance0
Sanctioned
₹50,000
Delay
592d
Cost deviation
0%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 592 days beyond expected completionPublished dates