Completion of 3rd Floor Construction, Yadav Dharmshala, and

Religious & Cultural

Haryana / HISAR — HISAR(DEPUTY COMMISSIONER HISSAR_IDA) · Rao Inderjit Singh (GURGAON)

Completion of 3rd Floor Construction, Yadav Dharmshala, and Installation of Rooftop Solar Power Plant

Overall risk score
56/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication0
Agency37
Compliance0
Sanctioned
₹15.00 L
Delay
323d
Cost deviation
165%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹1,499,787 against a ₹566,737 median for Religious & Cultural works in HISAR (165% above, 19 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 323 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.