Sewerage line upto the Pond at village Rai Takhana, Karnal
Water
Haryana / KARNAL — KARNAL(DEPUTY COMMISSIONER KARNAL) · Sanjay Bhatia (KARNAL)
Overall risk score
38/100
Blended from the five components below, each weighted as shown.
Risk components
Cost43
Delay100
Duplication0
Agency15
Compliance0
Sanctioned
₹8.00 L
Delay
595d
Cost deviation
—
Fewer than 8 comparable works in this district and sector
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
- 595 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.