Construction of Library Building at Bharat Nagar, Bagh Amber
Education
Telangana / HYDERABAD — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) · G Kishan Reddy (SECUNDERABAD)
Construction of Library Building at Bharat Nagar, Bagh Amberpet Division.
Overall risk score
55/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency33
Compliance0
Sanctioned
₹34.50 L
Delay
597d
Cost deviation
248%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹3,450,000 against a ₹990,000 median for Education works in HYDERABAD (248% above, 75 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 597 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.