Construction of 1st floor skill development , Chintal Basti

Community Buildings

Telangana / HYDERABAD — HYDERABAD(DISTRICT COLLECTOR HYDERABAD_IDA) · G Kishan Reddy (SECUNDERABAD)

Construction of 1st floor skill development , Chintal Basti Division, Khairatabad Assembly Constituency.(SC)

Overall risk score
47/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost68
Delay100
Duplication0
Agency33
Compliance0
Sanctioned
₹23.70 L
Delay
603d
Cost deviation
19%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
  • 603 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.