Road Upgrading Work in Chepdaguda Road to Gram Panchyat Gadh
Roads & Paving
Chhattisgarh / BASTAR — BASTAR(DISTRICT COLLECTOR BASTAR_IDA) · Deepak Baij (BASTAR)
Road Upgrading Work in Chepdaguda Road to Gram Panchyat Gadhiya
Overall risk score
53/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency23
Compliance0
Sanctioned
₹15.00 L
Delay
610d
Cost deviation
114%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,500,000 against a ₹700,000 median for Roads & Paving works in BASTAR (114% above, 70 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 610 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.