Road Upgrading Work in Laxman para to Todenar road, 1635 Met

Roads & Paving

Chhattisgarh / BASTAR — BASTAR(DISTRICT COLLECTOR BASTAR_IDA) · Deepak Baij (BASTAR)

Road Upgrading Work in Laxman para to Todenar road, 1635 Meter, Gram Panchyat Marikoder

Overall risk score
53/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication0
Agency23
Compliance0
Sanctioned
₹19.95 L
Delay
610d
Cost deviation
185%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹1,995,000 against a ₹700,000 median for Roads & Paving works in BASTAR (185% above, 70 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 610 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.