Balance Commuinity Bhavana building work at Kasaba hobli Th
Community Buildings
Karnataka / HASSAN — HASSAN(DEPUTY COMMISSIONER HASSAN_IDA) · Prajwal Revanna (HASSAN)
Balance Commuinity Bhavana building work at Kasaba hobli Thirupathi SC Colony Kasaba Hobli Agunda GP Arasikere Taluk
Overall risk score
51/100
Blended from the five components below, each weighted as shown.
Risk components
Cost28
Delay100
Duplication31
Agency85
Compliance0
Sanctioned
₹2.50 L
Delay
610d
Cost deviation
-17%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- 610 days beyond expected completionPublished dates
- 10 payments still in progress, oldest 633 daysPayment records
Decision trail
Nobody has recorded a decision on this work yet.
Reads as a near-duplicate of work #148408 (sentence-embedding similarity 0.96, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)