Improvement of Colony Sahi Kata at Tabda
Roads & Paving
Odisha / DEBAGADA — Debagada(District Collector Deogarh_IDA) · Nitesh Ganga Deb (SAMBALPUR)
Overall risk score
48/100
Blended from the five components below, each weighted as shown.
Risk components
Cost80
Delay100
Duplication0
Agency20
Compliance0
Sanctioned
₹9.00 L
Delay
616d
Cost deviation
80%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹900,000 against a ₹500,000 median for Roads & Paving works in DEBAGADA (80% above, 86 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 616 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.