Kasauti can only be opened on a desktop or laptop.

Open this link on a larger screen to see the verification queue.

← Back to works

Construction of Hall for Library in Saini Dharamshala.

Education

Haryana / KAITHAL — KAITHAL(DC CUM NODAL OFFICERS MPLADS) · Nayab Singh (KURUKSHETRA)

Overall risk score
45/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost53
Delay100
Duplication0
Agency43
Compliance0
Sanctioned
₹11.00 L
Delay
623d
Cost deviation
23%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
  • 623 days beyond expected completionPublished dates
  • Implementing agency has a 43% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.