Construction of Drain from Devan Kisku's House to Majistrate

Drainage & Sanitation

Jharkhand / DEOGHAR — DEOGHAR(DEPUTY COMMISSIONER DEOGHAR_IDA) · Sunil Soren (DUMKA)

Construction of Drain from Devan Kisku's House to Majistrate Kisku's House

Overall risk score
48/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost30
Delay100
Duplication0
Agency100
Compliance0
Sanctioned
₹2.50 L
Delay
629d
Cost deviation
0%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 629 days beyond expected completionPublished dates
  • 100% of this agency's ₹11,166,162 spend went to one vendor (JUNIOR ENGINEER DISTRICT BOARD DEOGHAR), across 1 vendor and 41 transactionsStatistics · Herfindahl-Hirschman index

Decision trail

Nobody has recorded a decision on this work yet.