Construction of Nala (Jal Nikashi) Pani Tanki to Kali Mandir
Water
Bihar / BUXAR — BUXAR(DISTRICT PLANNING OFFICER BUXAR_IDA) · Ashwini Kumar Choubey (BUXAR)
Construction of Nala (Jal Nikashi) Pani Tanki to Kali Mandir SC/ST Basti in Village Goovindpur
Overall risk score
55/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency33
Compliance0
Sanctioned
₹15.00 L
Delay
631d
Cost deviation
200%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,500,000 against a ₹499,512 median for Water works in BUXAR (200% above, 15 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 631 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.