Construction of CC Road at Nathaguda of Dasmanthpur G.P unde
Roads & Paving
Odisha / KORAPUT — KORAPUT(District Collector Koraput_IDA) · Saptagiri Sankar Ulaka (KORAPUT)
Construction of CC Road at Nathaguda of Dasmanthpur G.P under Boipariguda Block
Overall risk score
41/100
Blended from the five components below, each weighted as shown.
Risk components
Cost53
Delay100
Duplication0
Agency18
Compliance0
Sanctioned
₹2.50 L
Delay
827d
Cost deviation
0%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
- 827 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.