Completion of Boundary wall with drain at Dolagobinda High S
Drainage & Sanitation
Odisha / BALESHWAR — Baleshwar(DISTRICT COLLECTOR BALESHWAR_IDA) · Sulata Deo (Sitting Rajya Sabha)
Completion of Boundary wall with drain at Dolagobinda High School, Dhubagadia Panchayat Muruna Simulia
Overall risk score
53/100
Blended from the five components below, each weighted as shown.
Risk components
Cost50
Delay59
Duplication100
Agency39
Compliance0
Sanctioned
₹3.00 L
Delay
106d
Cost deviation
50%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹300,000 against a ₹200,000 median for Drainage & Sanitation works in BALESHWAR (50% above, 11 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 106 days beyond expected completionPublished dates
- 100% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)
Decision trail
Nobody has recorded a decision on this work yet.
Reads as a near-duplicate of work #11208 (sentence-embedding similarity 1.00, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)