construction of 100 fit ghat in pupunki kevat goraiya

Religious & Cultural

Jharkhand / BOKARO — BOKARO(DEPUTY COMMISSIONER BOKARO_IDA) · Pashupati Nath Singh (DHANBAD)

Overall risk score
45/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost36
Delay100
Duplication0
Agency73
Compliance0
Sanctioned
₹1.50 L
Delay
674d
Cost deviation
-46%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 674 days beyond expected completionPublished dates
  • Implementing agency has a 73% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.