Construction of Compound Wall in DIndigul Corporation volley

Boundary & Protection

Tamil Nadu / DINDIGUL — DINDIGUL(DISTRICT COLLECTOR DINDIGUL_IDA) · P. Velusamy (DINDIGUL)

Construction of Compound Wall in DIndigul Corporation volley ball ground located in 5th ward 10th cross RM Colony

Overall risk score
42/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost59
Delay100
Duplication0
Agency15
Compliance0
Sanctioned
₹12.00 L
Delay
692d
Cost deviation
—
Fewer than 8 comparable works in this district and sector
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
  • 692 days beyond expected completionPublished dates

Decision trail