Construction of Samudayik Bhawan nirman village Basanpani ke

Community Buildings

Madhya Pradesh / NARSIMHAPUR — Narsimhapur(DISTRICT COLLECTOR NARSINGHPUR_IDA) · Faggan Singh Kulaste (MANDLA)

Construction of Samudayik Bhawan nirman village Basanpani ke tapariya tela me

Overall risk score
57/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay100
Duplication0
Agency49
Compliance0
Sanctioned
₹3.00 L
Delay
710d
Cost deviation
100%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹300,000 against a ₹150,000 median for Community Buildings works in NARSIMHAPUR (100% above, 180 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 710 days beyond expected completionPublished dates
  • Implementing agency has a 49% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.