Construction of Road from Gurukunta to Pomal ZP road 1/900 t

Roads & Paving

Telangana / MAHABUBNAGAR — MAHABUBNAGAR(DISTRICT COLLECTOR MAHABUBNAGAR_3) · Srinivas Reddy Manne (MAHABUBNAGAR)

Construction of Road from Gurukunta to Pomal ZP road 1/900 to 2/530 km of Gurukunta (V) Nawabpet (M). Bit-8.

Overall risk score
57/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost33
Delay100
Duplication87
Agency43
Compliance0
Sanctioned
₹5.00 L
Delay
623d
Cost deviation
0%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 623 days beyond expected completionPublished dates
  • 99% similarity with another nearby workAI · Sentence-BERT embeddings (all-MiniLM-L6-v2)
  • Implementing agency has a 43% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.

Reads as a near-duplicate of work #27628 (sentence-embedding similarity 0.99, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)