Construction of community centers and community Building in
Community Buildings
Chhattisgarh / RAIGARH — RAIGARH(DISTRICT COLLECTOR RAIGARH_IDA) · Gomati Sai (RAIGARH)
Construction of community centers and community Building in Village Chaple
Overall risk score
48/100
Blended from the five components below, each weighted as shown.
Risk components
Cost61
Delay100
Duplication0
Agency48
Compliance0
Sanctioned
₹2.50 L
Delay
1,027d
Cost deviation
-58%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
- 1027 days beyond expected completionPublished dates
- Implementing agency has a 48% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.