← Back to works

In village Tilaulikala electrification was carried out with

Street Lighting

Uttar Pradesh / SONBHADRA — SONBHADRA(DISTRICT MAGISTRATE SONBHADRA_IDA) · Pakauri Lal (ROBERTSGANJ)

In village Tilaulikala electrification was carried out with a 10 KVA transformer from the main line near the house of Manish Kumar Gupta son of Ramgopal Gupta

Overall risk score
46/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost68
Delay100
Duplication0
Agency24
Compliance0
Sanctioned
₹42,000
Delay
1,060d
Cost deviation
-70%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
  • 1060 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.