phase ist construction of flood protection work at mohalla c

Boundary & Protection

Jammu And Kashmir / POONCH — POONCH(Deputy Commissioner Poonch_IDA) · Mian Altaf Ahmad (ANANTNAG)

phase ist construction of flood protection work at mohalla chwani Bakerwalan ward no 6 Gursai Harmutta block Mendhar poonch

Overall risk score
25/100
Blended from the five components below, each weighted as shown.
LOW

Risk components

Cost100
Delay0
Duplication0
Agency2
Compliance0
Sanctioned
₹6.00 L
Delay
0d
Cost deviation
100%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹600,000 against a ₹300,000 median for Boundary & Protection works in POONCH (100% above, 11 peer works)Peer comparison · sector labelled by Gemini Flash Lite

Decision trail

Nobody has recorded a decision on this work yet.