Construction of Community Centre in Tola Hohenhe of Panchaya

Community Buildings

Jharkhand / HAZARIBAGH — HAZARIBAGH(DEPUTY COMMISSIONER HAZARIBAGH_IDA) · Jayant Sinha (HAZARIBAGH)

Construction of Community Centre in Tola Hohenhe of Panchayat Honhemorha

Overall risk score
51/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost43
Delay100
Duplication0
Agency100
Compliance0
Sanctioned
₹5.00 L
Delay
722d
Cost deviation
0%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • Unusual combination of sanctioned amount, delay and spending pattern — flagged by an isolation forest fitted over every work, not by any single figure being out of rangeAI · Isolation Forest (scikit-learn)
  • 722 days beyond expected completionPublished dates
  • 100% of this agency's ₹39,899,950 spend went to one vendor (RAJ KUMAR SAGAR), across 1 vendor and 97 transactionsStatistics · Herfindahl-Hirschman index

Decision trail

Nobody has recorded a decision on this work yet.