Allahabad loksabha Kshetra Roads construction
Roads & Paving
Uttar Pradesh / PRAYAGRAJ — PRAYAGRAJ(DISTRICT MAGISTRAE ALLAHABAD_IDA) · Ujjwal Raman Singh (ALLAHABAD)
Overall risk score
44/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay38
Duplication0
Agency60
Compliance0
Sanctioned
₹1.68 Cr
Delay
69d
Cost deviation
2124%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹16,757,000 against a ₹753,500 median for Roads & Paving works in PRAYAGRAJ (2124% above, 120 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- Implementing agency has a 60% delay rate across its projectsStated compliance rule
Decision trail
Nobody has recorded a decision on this work yet.