construction off hall indoor badmintion cort

Community Buildings

Rajasthan / BEAWAR — Beawar(DISTRICT COLLECTOR Beawar_IDA) · Mahima Kumari Mewar (RAJSAMAND)

Overall risk score
47/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay47
Duplication0
Agency68
Compliance0
Sanctioned
₹10.00 L
Delay
85d
Cost deviation
100%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹1,000,000 against a ₹500,000 median for Community Buildings works in BEAWAR (100% above, 24 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 85 days beyond expected completionPublished dates
  • Implementing agency has a 68% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.