Gorahi Main Line Electrification from Shakuntala Maurya's farm to Kamleshwar's ,s/o Kamalnath's farm, 11 pole 25 KVA transformer.

Overall risk score
51/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost88
Delay100
Duplication0
Agency24
Compliance0
Sanctioned
₹2.62 L
Delay
728d
Cost deviation
88%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹262,000 against a ₹139,000 median for Street Lighting works in SONBHADRA (88% above, 825 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 728 days beyond expected completionPublished dates

Decision trail