Construction of SC Choupal in Village Rampur
Community Buildings
Haryana / AMBALA — AMBALA(DEPUTY COMMISSIONER AMBALA_IDA) · Varun Chaudhry (AMBALA)
Overall risk score
45/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay66
Duplication0
Agency26
Compliance0
Sanctioned
₹12.00 L
Delay
118d
Cost deviation
140%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,200,000 against a ₹500,000 median for Community Buildings works in AMBALA (140% above, 47 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 118 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.