Construction of Additional Room and halls in the existing Pu
Community Buildings
Andhra Pradesh / CHITTOOR — CHITTOOR(DISTRICT COLLECTOR CHITTOOR_IDA) · P V Midhun Reddy (RAJAMPET)
Construction of Additional Room and halls in the existing Public Community Building Bandakindapalli (V and G.P)
Overall risk score
44/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay68
Duplication0
Agency14
Compliance0
Sanctioned
₹70.00 L
Delay
122d
Cost deviation
1300%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹7,000,000 against a ₹500,000 median for Community Buildings works in CHITTOOR (1300% above, 59 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 122 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.