Construction of Multipurpose Activity Centre at Kumaradevam

Community Buildings

Andhra Pradesh / EAST GODAVARI — EAST GODAVARI(DISTRICT COLLECTOR, EAST GODAVARI) · D. Purandeswari (RAJAHMUNDRY)

Construction of Multipurpose Activity Centre at Kumaradevam Village

Overall risk score
49/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay69
Duplication0
Agency42
Compliance0
Sanctioned
₹50.00 L
Delay
125d
Cost deviation
100%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹5,000,000 against a ₹2,500,000 median for Community Buildings works in EAST GODAVARI (100% above, 38 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 125 days beyond expected completionPublished dates
  • Implementing agency has a 42% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.