Construction of gali from culvert near sumit house to Chowk

Roads & Paving

Haryana / PANIPAT — PANIPAT(DC CUM NODAL OFFICER MPLADS) · Manohar Lal (KARNAL)

Overall risk score
31/100
Blended from the five components below, each weighted as shown.
LOW

Risk components

Cost23
Delay70
Duplication0
Agency52
Compliance0
Sanctioned
₹5.00 L
Delay
126d
Cost deviation
-28%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 126 days beyond expected completionPublished dates
  • Implementing agency has a 52% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.