Near Gulmohar Society Ranade Road, Dadar (W)

Roads & Paving

Maharashtra / MUMBAI — MUMBAI(DISTRICT COLLECTOR MUMBAI CITY_IDA) · Anil Yeshwant Desai (MUMBAI SOUTH CENTRAL)

Overall risk score
42/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost82
Delay67
Duplication0
Agency32
Compliance0
Sanctioned
₹40.00 L
Delay
121d
Cost deviation
82%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹4,000,000 against a ₹2,199,166 median for Roads & Paving works in MUMBAI (82% above, 74 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 121 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.