Construction of boundary wall of village pond in village bha

Water

Punjab / PATIALA — PATIALA(DEPUTY COMMISSIONER PATIALA_IDA) · Dharamvira Gandhi (PATIALA)

Construction of boundary wall of village pond in village bhankhar, block bhunerheri, patiala

Overall risk score
45/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost88
Delay74
Duplication0
Agency32
Compliance0
Sanctioned
₹3.00 L
Delay
133d
Cost deviation
88%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹300,000 against a ₹160,000 median for Water works in PATIALA (88% above, 103 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 133 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.