Construction community centre at with toilet Manjhi Tola, pa
Drainage & Sanitation
Bihar / ROHTAS — ROHTAS(District Planning Officer Rohtas_IDA) · Sudhakar Singh (BUXAR)
Construction community centre at with toilet Manjhi Tola, pachauli
Overall risk score
46/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay81
Duplication0
Agency7
Compliance0
Sanctioned
₹15.00 L
Delay
146d
Cost deviation
200%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹1,500,000 against a ₹500,000 median for Drainage & Sanitation works in ROHTAS (200% above, 23 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 146 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.