Construction of one classroom of Birupa High School at Champ

Education

Odisha / KATAKA — Kataka(DISTRICT COLLECTOR CUTTACK_IDA) · Baijayant Panda (KENDRAPARA)

Construction of one classroom of Birupa High School at Champapur, Gopinathpur GP, Salipur Block, District Cuttack

Overall risk score
42/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost60
Delay90
Duplication0
Agency28
Compliance0
Sanctioned
₹8.00 L
Delay
162d
Cost deviation
60%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹800,000 against a ₹500,000 median for Education works in KATAKA (60% above, 115 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 162 days beyond expected completionPublished dates

Decision trail

Nobody has recorded a decision on this work yet.