Construction of I.C.D.S Building, Executive Agency - E.O Raj

Community Buildings

West Bengal / BIRBHUM — BIRBHUM(DISTRICT MAGISTRATE BIRBHUM_IDA) · Satabdi Roy (BIRBHUM)

Construction of I.C.D.S Building, Executive Agency - E.O Rajnagar Panchayat Samitte

Overall risk score
32/100
Blended from the five components below, each weighted as shown.
LOW

Risk components

Cost32
Delay93
Duplication0
Agency8
Compliance0
Sanctioned
₹6.50 L
Delay
167d
Cost deviation
-32%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 167 days beyond expected completionPublished dates

Decision trail