Construction of Shed or Room in Saraswati Higher Secondary S

Education

Madhya Pradesh / JABALPUR — JABALPUR(DISTRICT COLLECTOR JABALPUR_IDA) · Ashish Dubey (JABALPUR)

Construction of Shed or Room in Saraswati Higher Secondary School Ranjhi.

Overall risk score
54/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost100
Delay96
Duplication0
Agency37
Compliance0
Sanctioned
₹5.05 L
Delay
172d
Cost deviation
114%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹505,000 against a ₹236,500 median for Education works in JABALPUR (114% above, 32 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 172 days beyond expected completionPublished dates

Decision trail