Construction of PCC Road in Village- Balidangal in front of

Roads & Paving

Jharkhand / DUMKA — DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) · Nalin Soren (DUMKA)

Construction of PCC Road in Village- Balidangal in front of ITI Villagers Road near Timiti Marandi House

Overall risk score
48/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost67
Delay98
Duplication0
Agency48
Compliance0
Sanctioned
₹5.00 L
Delay
176d
Cost deviation
67%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹500,000 against a ₹300,000 median for Roads & Paving works in DUMKA (67% above, 319 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 176 days beyond expected completionPublished dates
  • Implementing agency has a 48% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.