Construction of PCC Road in Village- Bhoktandih Aadiwasi Tol

Roads & Paving

Jharkhand / DUMKA — DUMKA(DEPUTY COMMISSIONER DUMKA_IDA) · Nalin Soren (DUMKA)

Construction of PCC Road in Village- Bhoktandih Aadiwasi Tola, Panchayat- Khadukadma

Overall risk score
45/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost24
Delay98
Duplication38
Agency48
Compliance0
Sanctioned
₹2.50 L
Delay
176d
Cost deviation
-17%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • 176 days beyond expected completionPublished dates
  • Implementing agency has a 48% delay rate across its projectsStated compliance rule

Decision trail

Nobody has recorded a decision on this work yet.

Reads as a near-duplicate of work #117046 (sentence-embedding similarity 0.96, measured by all-MiniLM-L6-v2 on meaning rather than shared words; two works can legitimately share a description, so this is a prompt to check, not a finding)