Const. Boundary walls of Near Orang Anchalik Bathou Mandir

Religious & Cultural

Assam / UDALGURI — UDALGURI(DEPUTY COMMISSIONER Udalguri_IDA) · Dilip Saikia (Darrang-Udalguri)

Overall risk score
47/100
Blended from the five components below, each weighted as shown.
MEDIUM

Risk components

Cost67
Delay100
Duplication0
Agency37
Compliance0
Sanctioned
₹5.00 L
Delay
187d
Cost deviation
67%
Work status
Recommended

AI powered · gemini-flash-liteWhy was this flagged?

  • ₹500,000 against a ₹300,000 median for Religious & Cultural works in UDALGURI (67% above, 86 peer works)Peer comparison · sector labelled by Gemini Flash Lite
  • 187 days beyond expected completionPublished dates

Decision trail