instalation of highmust light at Bagdangabazer Mousumi 8pcs
Street Lighting
West Bengal / SOUTH 24 PARGANAS — South 24 Parganas(DISTRICT MAGISTRATE SOUTH TWENTY FOUR PARGANAS_IDA) · Bapi Haldar (MATHURAPUR)
instalation of highmust light at Bagdangabazer Mousumi 8pcs light
Overall risk score
53/100
Blended from the five components below, each weighted as shown.
Risk components
Cost100
Delay100
Duplication0
Agency22
Compliance0
Sanctioned
₹5.22 L
Delay
188d
Cost deviation
201%
Work status
Recommended
AI powered · gemini-flash-liteWhy was this flagged?
- ₹522,305 against a ₹173,411 median for Street Lighting works in SOUTH 24 PARGANAS (201% above, 528 peer works)Peer comparison · sector labelled by Gemini Flash Lite
- 188 days beyond expected completionPublished dates
Decision trail
Nobody has recorded a decision on this work yet.